Securing Temporary Use Permit (TUP)

Department/Office: City Planning and Development Office
Classification: Complex to Highly Technical
Type of Transaction: G2C - Government to Citizens, G2B - Government to Businesses, and G2G - Government to Government
Who May Avail: Any Resident

About the Service

A Temporary Use Permit (TUP) allows the establishment of a use or activity not normally permitted under the zoning regulations for a specific area. This permit is issued on a case-to-case basis and is subject to conditions to ensure compatibility with surrounding properties and compliance with city planning standards.

What you need to prepare:

CHECKLIST OF REQUIREMENTS

WHERE TO SECURE

  • A complete description of the proposed project showing in the processes and machineries involved therein
 
  • A vicinity map showing existing facilities, structures and uses from 100 meter radius distance from the proposed site
 
  • A certificate obtained from the homeowner's association and/or barangay to the said effect that said organizations pose no objection to the establishment of the proposed activity
  • Barangay Hall

Steps

CLIENT STEPS

AGENCY ACTION (DETAILED)

AGENCY ACTION (SIMPLIFIED)

FEES TO BE PAID

PROCESSING TIME

PERSON RESPONSIBLE

1. Submit Application and Requirements to CPDO.

Frontline personnel receives and checks for completeness of requirements.

   

10 minutes

BERNIE L. ALAMER
Administrative Aide III

 

SIEGFRED S. SERVINO
Administrative Aide III

 

TRISHA-MARIE O. ALBEUS
Project Development Officer II

 

NESSY P. SALES
Statistician II/Acting Zoning Administrator

 

The omission of Steps 2 through 3 is permissible for applications related to Locational Clearance and Business Permits, provided these steps have already been conducted.

The omission of Steps 2 through 3 is permissible for applications related to Locational Clearance and Business Permits, provided these steps have already been conducted.

  
 

2. Review of Documents.

- Zoning Compliance Verification. Zoning official checks if the proposed business/project is in accordance with the classification specified in the land use plan.

- Tax Map Verification if needed

- Regulatory Compliance Check. Recheck compliance with other regulations


(a) If the application conforms to the land use classification of the subject property, application will be prompted to proceed to Step 5.

(b) However, If the review raises a query regarding zoning compliance that cannot be resolved through the submitted documents, the application will be endorsed for site inspection (Step 3).

2. Review of Documents.

A zoning official will review if your application complies with all zoning and other regulations.


(a) If compliant, you will be notified to pay the Technical Evaluation Fee and proceed with the application process (Step 5).

(b) If not, your application will be endorsed for site inspection (Step 3).

 

5 minutes

 

3. Site Inspection

If site inspection is required, frontline officer refers the same to the Zoning Administrator, zoning official or their authorized representative.


Site inspection is usually required for new enterprises.

3. Site Inspection

 

Minimum of 5 days

SIEGFRED S. SERVINO
Administrative Aide III

 

MARIO CHRISTOPHER G. GUMBA
Engineer I

 

4. Evaluation

Technical team evaluates project impact on surrounding areas, drafts technical evaluation documents

4. Evaluation

Technical team evaluates project impact on surrounding areas, drafts technical evaluation documents

 

Minimum of 5 days

MARIO CHRISTOPHER G. GUMBA
Engineer I

 

TRISHA-MARIE O. ALBEUS
Project Development Officer II

 

NESSY P. SALES
Statistician II/Acting Zoning Administrator

 

5. Submission of consolidated evaluation report to SP and members of the Land Use Committee

5. Submission of consolidated evaluation report to SP and members of the Land Use Committee

 

30 minutes *provided that copies are already available

MARIO CHRISTOPHER G. GUMBA
Engineer I

 

TRISHA-MARIE O. ALBEUS
Project Development Officer II

 

NESSY P. SALES
Statistician II/Acting Zoning Administrator

 

WILFREDO B. PRILLES, JR.
City Planning and Development Coordinator

 

6. Deliberation and Approval by SP through the Land Use Committee

6. Deliberation and Approval by SP through the Land Use Committee

 

Dependent on SP schedule

Land Use Committee

 

Sangguniang Panlungsod

 

7. Issuance of Resolution

Assuming it is approved by SP, signed by Secretary to the SP, City Vice-Mayor and City Mayor

7. Issuance of Resolution

Assuming it is approved by SP, signed by Secretary to the SP, City Vice-Mayor and City Mayor

  

TOTAL

P

10 days 45 minutes + LUC/SP schedule

 
For inquiries, please contact: Mr. Wilfredo B. Prilles Jr. /CGDH I / CPD Coordinator I
Address:

City Planning and Development Office
208 – 2/F Main City Hall Bldg., Naga City Hall Complex, Juan Q. Miranda Ave., Concepcion Pequeña, Naga City
 

Contact Number(s):
☎ PLDT: +63-54-871-2050 (Local: 2080 )
☎ GLOBE: +63-54-205-2980 (Local: 2080 )

HELP US SERVE YOU BETTER!

If you have recently transacted with this office, we'd like to know how it went, This Client Satisfaction Measurement (CSM) tracks the customer experience of government offices. Your feedback will help this office improve its services. Clicking on the link will redirect you to a survey page.

THE NAGA CITY iGOVERNANCE OFFICE