A Temporary Use Permit (TUP) allows the establishment of a use or activity not normally permitted under the zoning regulations for a specific area. This permit is issued on a case-to-case basis and is subject to conditions to ensure compatibility with surrounding properties and compliance with city planning standards.
CHECKLIST OF REQUIREMENTS | WHERE TO SECURE |
| |
| |
|
|
CLIENT STEPS | AGENCY ACTION (DETAILED) | AGENCY ACTION (SIMPLIFIED) | FEES TO BE PAID | PROCESSING TIME | PERSON RESPONSIBLE |
1. Submit Application and Requirements to CPDO. Frontline personnel receives and checks for completeness of requirements. | 10 minutes | BERNIE L. ALAMER
SIEGFRED S. SERVINO
TRISHA-MARIE O. ALBEUS
NESSY P. SALES | |||
The omission of Steps 2 through 3 is permissible for applications related to Locational Clearance and Business Permits, provided these steps have already been conducted. | The omission of Steps 2 through 3 is permissible for applications related to Locational Clearance and Business Permits, provided these steps have already been conducted. | ||||
2. Review of Documents. - Zoning Compliance Verification. Zoning official checks if the proposed business/project is in accordance with the classification specified in the land use plan. - Tax Map Verification if needed - Regulatory Compliance Check. Recheck compliance with other regulations (a) If the application conforms to the land use classification of the subject property, application will be prompted to proceed to Step 5. (b) However, If the review raises a query regarding zoning compliance that cannot be resolved through the submitted documents, the application will be endorsed for site inspection (Step 3). | 2. Review of Documents. A zoning official will review if your application complies with all zoning and other regulations. (a) If compliant, you will be notified to pay the Technical Evaluation Fee and proceed with the application process (Step 5). (b) If not, your application will be endorsed for site inspection (Step 3). | 5 minutes | |||
3. Site Inspection If site inspection is required, frontline officer refers the same to the Zoning Administrator, zoning official or their authorized representative. Site inspection is usually required for new enterprises. | 3. Site Inspection | Minimum of 5 days | SIEGFRED S. SERVINO
MARIO CHRISTOPHER G. GUMBA | ||
4. Evaluation Technical team evaluates project impact on surrounding areas, drafts technical evaluation documents | 4. Evaluation Technical team evaluates project impact on surrounding areas, drafts technical evaluation documents | Minimum of 5 days | MARIO CHRISTOPHER G. GUMBA
TRISHA-MARIE O. ALBEUS
NESSY P. SALES | ||
5. Submission of consolidated evaluation report to SP and members of the Land Use Committee | 5. Submission of consolidated evaluation report to SP and members of the Land Use Committee | 30 minutes *provided that copies are already available | MARIO CHRISTOPHER G. GUMBA
TRISHA-MARIE O. ALBEUS
NESSY P. SALES
WILFREDO B. PRILLES, JR. | ||
6. Deliberation and Approval by SP through the Land Use Committee | 6. Deliberation and Approval by SP through the Land Use Committee | Dependent on SP schedule | Land Use Committee
Sangguniang Panlungsod | ||
7. Issuance of Resolution Assuming it is approved by SP, signed by Secretary to the SP, City Vice-Mayor and City Mayor | 7. Issuance of Resolution Assuming it is approved by SP, signed by Secretary to the SP, City Vice-Mayor and City Mayor | ||||
TOTAL | P | 10 days 45 minutes + LUC/SP schedule | |||
City Planning and Development Office
208 – 2/F Main City Hall Bldg., Naga City Hall Complex, Juan Q. Miranda Ave., Concepcion Pequeña, Naga City

If you have recently transacted with this office, we'd like to know how it went, This Client Satisfaction Measurement (CSM) tracks the customer experience of government offices. Your feedback will help this office improve its services. Clicking on the link will redirect you to a survey page.
THE NAGA CITY iGOVERNANCE OFFICE