Enterprises are required to secure a Building Clearance upon application for Business Permit to ensure that the enterprise complied with the provisions of the National Building Code, building related laws and ordinances.
|
||||||||||
CLIENT STEPS | AGENCY ACTION | FEES TO BE PAID | PROCESSING TIME | PERSON RESPONSIBLE |
1. Proceed to the CEO / OBO Go to a frontline staff and present your Business License Application Form | 2 minutes | GRACE P. LAÑADA Administrative Aide I (Job Order) ENGR. EVANGELINE P. PASABA Engineer II (CE) | ||
FOR NEW ENTERPRISES | ||||
1. Submit Requirements Submit the detailed information of the business and sketch of location for site inspection and picture of the building or its façade. | 3 minutes | ENGR. ELMER T. ALBO CGADH I Assistant City Engineer ENGR. GREGORY D. MORENO ENGR. NELSON B. PRILLES ARCH. JOHN DARYL M. MARTINEZ Architect I (COS) | ||
2. Documents Review Technical staff review documents, if found in order, proceed to Step 7. | 5 minutes | |||
3. Building Inspection (Optional) If building inspection is required, (Site inspection is usually required for new enterprises), the applicant must submit the detailed information of the business and sketch of location for site inspection. | 30 minutes | |||
4. Inquire the Result of Inspection Applicant inquires the result of inspection a day after the technical staffs conduct building inspection. He/she will receives an inspection report that list violations of the codes and ordinances found in the building | 5 minutes | |||
5. Request for re-inspection The applicant will inform the building inspectors that corrections have been done for re-inspection. | 5 minutes | |||
6. Re-inspection of the Building Technical staff conduct re-inspection if the deficiencies stated in the inspection report have been corrected. | 15 minutes | |||
7. Assessment and Approval Once all the requirements have been complied with, an assessment and clearance will be given to the applicant. | 5 minutes | |||
TOTAL | P | 1 hour and 10 minutes | ||
City Engineer’s Office, 106 – G/F Main City Hall Bldg., Naga City Hall Complex, Juan Q. Miranda Ave., Concepcion Pequeña, Naga City